Project Status: Completed Client: Flow Logistics - Ikea Consultant: MZECH (Design Consultant) / V3 Middle East Engineering Consultants (Design Review Consultant) Main Contractor: Amana Saudi Total Build up Area: 7,000m2 Floor Type & Category: Clad Racking Execution Period: January 2016
The floor wasn’t isolated from the structure as a ‘normal’ floor slab is, but forms the foundation for the entire building. So with this clad rack floor, it was constructed outside, and exposed to the elements. It’s also much thicker with more steel than a conventional "slab on grade."
CoGri Middle East - Osis Group JV had 15 men on site for 16 days to complete the work, and also flew a supervisor over from the UK for design conformity and surveying.
The work was completed at the beginning of 2016, with great success.